Decision details

Options appraisal for the delivery and operation of an electric vehicle charging network

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Decision:

1.    That capital expenditure of £120,000 utilising the capital budget allocated in the Capital Programme (CAB3209) be approved for the installation of an electric vehicle charging network in accordance with option 3 set out in report CAB3206.

 

2.    That authority be delegated to the Service Lead: Legal to award and enter into a contract with JoJu Charging, a subsidiary of JoJu Ltd, using the Hampshire County Council (HCC) ‘Framework Agreement for the Provision of Electric Vehicle Charging Points’ and associated legal agreements such as a lease.

 

3.    That proposals to extend the network of electric vehicle charging points to serve the Park and Ride sites, the new leisure centre, tenants living in the Council’s own property portfolio over the next year be supported (subject to financial appraisal), and to work with Hampshire County Council in delivering an on street charging infrastructure by 2021/22 as part of the Winchester Movement Strategy.

Reason Key: Expenditure > £250,000;

Wards Affected: (All Wards);

Contact: Simon Finch, Corporate Head: Regulatory Email: sfinch@winchester.gov.uk.

Report author: Simon Finch

Publication date: 12/02/2020

Date of decision: 12/02/2020

Decided at meeting: 12/02/2020 - Cabinet

Effective from: 20/02/2020

Accompanying Documents:

 

Options appraisal for the delivery and operation of an electric vehicle charging network{sidenav}{content}