Decision:

1.            Subject to Council approval of the Budget and Capital Investment Strategy in February 2020, expenditure of £400,000 for 2020/21 as outlined in Appendix A of Report CAB3213, be approved.

 

2.            That the indicative programme for 2021/22 totalling £811,000 be noted as a basis for planning and preparing future works.

 

3.            That authority to make minor adjustments to the programme, in order to meet maintenance and operational needs of the car park service throughout the year as required, be delegated to the Corporate Head of Regulatory, in consultation with the Corporate Head of Asset Management and Cabinet Member for the Environment.

Reason Key: Expenditure > £250,000;

Wards Affected: (All Wards);

Contact: Andy Hickman, Head of Programme: Place Email: ahickman@winchester.gov.uk, Campbell Williams, Service Lead - Environmental Services Email: cawilliams@winchester.gov.uk.

Report author: Andy Hickman

Publication date: 22/01/2020

Date of decision: 22/01/2020

Decided at meeting: 22/01/2020 - Cabinet

Effective from: 30/01/2020

Accompanying Documents:

 