1.       That it be recommended to council to approve a capital budget of £610,000 to refurbish 59 Colebrook Street to provide temporary homeless accommodation, funded by £250k grant from HCC, £206k grant from LAHF, and £154k of prudential borrowing.*

 

That subject to Council approval of the budget:

2.       That capital expenditure of up to £610,000 be approved to refurbish 59 Colebrook Street to provide temporary homeless accommodation.

 

3.       That authority be delegated to the Strategic Director (responsible for Housing) to approve the tender evaluation model.

 

4.       That authority be delegated to the Strategic Director (responsible for Housing) to appoint the preferred contractor(s) following a competitive procurement process.  

 

 

5.       That authority be delegated to the Service Lead (Estates): to enter into all relevant agreements, to negotiate the contractual agreements and see them to completion to enable the conversion and refurbishment contract to be executed.

 

*NB recommendations to Council are not subject to call-in.

 

 

Reason Key: Expenditure > £250,000;

Wards Affected: St Michael;

Contact: Gillian Knight, Corporate Head: Housing (Interim) Email: gknight@winchester.gov.uk.

Report author: Gillian Knight

Publication date: 22/11/2023

Date of decision: 21/11/2023

Decided at meeting: 21/11/2023 - Cabinet

Effective from: 30/11/2023

Accompanying Documents:

 

59 Colebrook Street - refurbishment and conversion to shared accommodation for the use of Ukrainian and Afghanistan guests{sidenav}{content}