Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: Yes
1. That the progress achieved during the second quarter of 2019/20 be noted and the contents of the report be endorsed.
2. That capital expenditure of £350,000 be approved in respect of capital works on Chesil Multi-Storey car park.
3. That a supplementary capital budget and authority to incur expenditure of £350,000 in respect of the Durngate Flood Relief Scheme be approved.
4. That a supplementary capital budget and authority to incur expenditure of £135,000 in respect of Chilcomb Sports Ground Pavilion improvement be approved.
Reason Key: Significantly effect on 2 or more wards;
Wards Affected: (All Wards);
Contact: Lisa Kirkman, Strategic Director and Monitoring Officer Email: lkirkman@winchester.gov.uk.
Report author: Lisa Kirkman
Publication date: 23/12/2019
Date of decision: 23/12/2019
Decided at meeting: 23/12/2019 - Cabinet
Effective from: 03/01/2020
Accompanying Documents: