Decision details

New Homes scheme - Outline Business Case, Woodman Close, Sparsholt (less exempt appendix) (DD30)

Decision Maker: z Cabinet Member for Housing & Asset Management Decision Day - DISCONTINUED

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: No

Decision:

1.            That the Corporate Head of Asset Management be authorised to prepare and submit a planning application to the statutory planning authority to obtain planning permission for the construction of 5 properties at Woodman Close, Sparsholt, at an estimated cost of up to £50,000 to allow for any further investigative work and fees.  

 

2.            That the Corporate Head of Asset Management be authorised to invite tenders to undertake the design and build of 5 properties at Woodman Close, using a standard JCT Design and Build Contract.

 

3.            That the Corporate Head of Asset Management be authorised to negotiate and agree terms for easements, wayleaves and related agreements with utility providers, telecom/media suppliers, Highways Authority and neighbours in order to facilitate the development subject to final decision to proceed with the Scheme.

 

4.            That it be noted that a Final Business Case report would to be brought to Members after tenders are evaluated and the final tender price was known, to agree whether to proceed with the scheme, to final rent levels to be applied and to award and enter into a construction design and build contract with the preferred bidder.  

Reason Key: Expenditure > £250,000;

Wards Affected: Wonston & Micheldever;

Contact: Andrew Palmer, Head of New Homes Delivery Email: apalmer@winchester.gov.uk.

Report author: Andrew Palmer

Publication date: 05/07/2021

Date of decision: 05/07/2021

Decided at meeting: 05/07/2021 - z Cabinet Member for Housing & Asset Management Decision Day - DISCONTINUED

Accompanying Documents:

 

New Homes scheme - Outline Business Case, Woodman Close, Sparsholt (less exempt appendix) (DD30){sidenav}{content}