Issue - meetings

Hobbs View, Southbrook Cottages, Micheldever - Lessons Learned

Meeting: 19/11/2025 - Cabinet (Item 11.)

11. Hobbs View, Southbrook Cottages, Micheldever - Lessons Learned pdf icon PDF 259 KB

Decision:

That the reasons for the project overspend are noted, along with the points that Cabinet was asked to consider by the Scrutiny Committee, and that procurement and management of future projects seeks to learn from this pilot scheme.


Meeting: 13/11/2025 - The Scrutiny Committee (Item 8)

8 Hobbs View, Southbrook Cottages, Micheldever - Lessons Learned pdf icon PDF 73 KB

It is recommended that the committee scrutinise and comment on the content within the attached cabinet report, ref CAB3492, particularly the identified “lessons learned” which will be considered by cabinet at its meeting on the 19 November 2025.

Additional documents:

Minutes:

Councillor Mark Reach, Cabinet Member for Good Homes introduced the report which provided the lessons learned from the construction of six flats at Southbrook Cottages, Micheldever. The introduction included the following points.

 

  1. The project, which began in 2020, had an overspend of approximately 27% on total costs therefore a report to Scrutiny and Cabinet was required.
  2. The properties were built to Passivhaus Plus standard as a pilot development in support of the council’s Carbon Neutrality Action Plan objectives. The report detailed the reasons for the cost overrun and proposed actions to be considered for future projects.

 

Councillor Caroline Horrill addressed the committee and raised several points for the committee to consider which could be summarised as follows. She stated that while she was in favour of project reviews, she felt the report lacked the full history of the project. She felt that the decision to build to Passivhaus standard meant that the scheme was over-specified. Councillor Horrill highlighted that the report failed to include the loss of revenue to the Housing Revenue Account (HRA) during rectification works and made no reference to issues experienced by the Parish Council with the contractor. She concluded that the report was a lost opportunity as it had not sought input from ward councillors or the Parish Council.

 

Councillor Danny Lee addressed the committee and raised several points for the committee to consider which could be summarised as follows. He congratulated the housing team on delivering the project, which supported the council’s greener faster priorities. He acknowledged the cost overrun but noted it was a pilot project with a steep learning curve. He argued strongly that full Passivhaus certification was vital for future schemes as it provided quality assurance and eliminated the performance gap between a building’s design and actual energy efficiency. He stated that choosing not to certify future Passivhaus projects would be a poor decision and suggested a future comparative analysis could be undertaken against Modern Methods of Construction (MMC).

 

Ian Tait addressed the committee and raised several points for the committee to consider which could be summarised as follows. He wished tohighlight that the final project cost represented a 137% increase against the initial appraisal in 2020. He stated that the figures could not be justified, noting that the cost per square metre was more than double that of a commercial developer. Mr Tait advised the committee that the expenditure was from the HRA, funded by council tenants’ rent, and that he felt that tenants wanted more decent homes rather than expensive schemes such as this.

 

The committee was asked to scrutinise and comment on the content within the attached cabinet report, ref CAB3492, particularly the identified “lessons learned” which would be considered by cabinet at its meeting on 19 November 2025. The committee proceeded to ask questions and debate the report. In summary, the following matters were raised.

 

  1. A question was asked about the contract and why remedial works were not included within its original scope.
  2. Clarification was  ...  view the full minutes text for item 8

 

ems at meetings - Hobbs View, Southbrook Cottages, Micheldever - Lessons Learned{sidenav}{content}