The Forum received and noted the report of the Strategic Director which provided an update on progress with issues relating to the Kings Barton Development. The key issues within the report were reported and summarised as follows:

 

·         As of the date of the meeting, there were 205 occupations at Phase 1B of Kings Barton with only 18 units remaining unsold. All 89 affordable housing units in this phase had now been passed over to VIVID. Groundworks for the Phase 1B play area had now commenced.

 

·         Occupation of Phase 1A was due to begin late August 2019 and it was anticipated that the reserved matters application for Phase 2A would be submitted in mid July.  This would comprise 250 units to the north of Phase 1A.

 

·         The next two months would be an extremely busy period as a condition of the planning application was that all reserved matters applications must be submitted before 2 October 2019 to be valid. In addition to the Phase 2A application, CALA was preparing approximately nine further reserved matters applications to ensure this obligation was met. These further applications would be sufficient to be validated but they would not be immediately determined. A reserved matters application for the local centre would be included and would reflect previous consultations on the form and content but would be capable of further modification. This would be open to further discussion at a future Forum meeting and at a public meeting with dates to be confirmed. 

 

Members of the Forum asked a number of questions regarding the reserved matters applications and Section 106 requirements. Officers advised that reserved matters would be subject to normal consultation requirements as and when they were determined.

 

Members also agreed to undertake a regular site tour, ideally every three months with the first to take place before the end of September.

 

 

RESOLVED:

That the content of the report is noted.

 


 