M27 Junction 9 - Verbal Update

Minutes:

Patrick Bingham, Hampshire County Council provided the forum with a verbal update concerning the latest position regarding the M27 Junction 9 and  Parkway roundabout scheme. The update covered a range of issues including:

 

1.    that overall works were progressing well

2.    that the forecast completion was late September 2022

3.    that an opening event at the Solent Hotel was planned

4.    that resurfacing works would be causing some disruption for motorists and the latest information could be obtained here: https://www.hants.gov.uk/transport/transportschemes/m27junction9

5.    that vehicle restraint system and drainage works were taking place on Whiteley Way

6.    that permissions were being sought for parapet and Southern footway tie-in works

7.    that arrangements for future tree planting works were being discussed.

 

Members asked several questions and made comments regarding:

 

1.    the lack of lane and junction markings on the roundabout nearest the Solent Hotel

2.    the timescales for the works to the dual carriageway running between the Tesco store and the Solent Hotel

3.    the operation of the traffic lights on Whiteley Way and the junction with Curdridge Lane

4.    the extension of the cycle route from Junction 9 to Lidl.

 

These points were responded to by Mr Ingham who undertook to review any unresolved points raised and respond to members following the meeting.

 