Councillor Mark Reach, Cabinet
Member for Good Homes introduced the report, ref CAB3540 which set
out proposals for the Housing Revenue Account (HRA) Budget 2026/27
and the longer-term business plan regarding capital investment. The
introduction included the following points.
- The report was
produced following modelling and engagement with tenants, including
the TACT board, two members of which were present at the meeting
and a wider consultation which received 291 responses.
- The plan addressed
challenges arising from inflation, increased construction costs,
energy prices, and borrowing.
- The aim was to ensure
a housing service that was fit for purpose, providing tenants with
good, warm, safe, and secure homes that were economical to run and
met regulatory standards.
- The report set out
plans to protect the repairs and maintenance programme, retrofit
and decarbonisation plans, and the strategy for building or
acquiring further council homes.
- Savings of
approximately £1.1 million were identified within the
budget.
- The proposal followed
the rent setting guidelines from the Social Housing Regulator of
CPI plus 1%, equating to 4.8% for the period.
- Risks facing the HRA
in the medium term were outlined, primarily relating to
macroeconomic factors and central government funding.
- A verbal update would
be provided to Cabinet regarding a change to one of the savings
recommendations following a request from the TACT
board.
The committee was asked to
comment on the proposals within the attached cabinet report, ref
CAB3540, which was to be considered by the cabinet at its meeting
on 12 February 2026. The committee proceeded to ask questions and
debate the report. In summary, the following matters were
raised.
- A question was asked
regarding the table on page 44 regards “loss of
funding”, as it was felt that the numbers did not appear to
add up correctly.
- Further clarification
was sought regarding paragraph 11.9 and the full stock condition
survey, and whether any unexpected findings were
anticipated.
- Clarification was
requested regarding paragraph 11.66 and the wastewater treatment
plant upgrades, specifically which site was referred to in this
paragraph.
- Clarification was
requested on whether the council was moving towards full cost
recovery for sewage treatment, the progress in rationalising
resident charges, and if the issues regarding charging at Hobbs
Close would be addressed.
- Clarification was
sought regarding paragraph 1.6 and how the feedback from tenants,
including those who had exercised Right to Buy, had been
considered.
- A question was asked
regarding paragraph 11.64 and EPC targets, and how much the needs
of tenants for warmer homes and lower costs were considered in
prioritisation decisions.
- It was asked whether
the challenges regarding energy improvements and the Social Housing
Decarbonisation Fund (SHF) Programme Wave 3 funding had been
discussed at a recent the Cabinet Committee: Housing
meeting.
- Clarification was
sought regarding the change in approach to Department for Energy
Security and Net Zero (DESNZ) funding, noting that the proposal was
for the council to self-fund.
- Clarification was
requested on how many of the confirmed programme of 672 homes for
solar panel and battery installation had been
completed.
- A question was asked
regarding the target of 87% of stock to meet EPC-C by March 2028,
and what percentage of tenants were resistant to retrofit schemes
and what was a realistic target.
- Clarification was
sought regarding paragraph 11.8 and the average social rent for new
tenancies.
- A question was asked
regarding paragraph 11.9 and the stock condition survey
availability in mid-2026, and whether this should feed into the
2027/28 planning process rather than 2026/27.
These points were responded to
by Councillor Reach, Cabinet Member for Good Homes and Simon
Hendey, Strategic Director accordingly.
RESOLVED:
1.
That the report be noted.
2.
That whilst the committee had no specific
recommendations to forward to Cabinet, that cabinet considers the
committee’s comments raised during the discussion of the
item.