Minutes:
(i) Marketing had progressed for land parcel M1, while parcel M3 was delayed pending the outcome of the adjacent Blue Star Land planning application.
(ii) Confirmation was provided that the northern and southern allotments were complete, with final snagging works outstanding.
(iii) A new play area off the western link road was opened in December.
(iv) Planning approval for Town Park Phase B was received in December and a tender pack was being finalised for works to commence in 2026.
(v) Discussions with the developer for the local centre and community building remained ongoing.
(vi) Discussions were ongoing with the NHS regarding the health centre land and meetings were due to be scheduled. In respect of the extra care site, discussions were in place with Hampshire County Council to move forward over the next six months.
(vii) Infrastructure works to access the cricket pavilion commenced on 16 February with an estimated completion for the pavilion by 2027.
(viii) Updates were provided on the Blue Star Land planning application regarding responses to highways comments.
(ix) Confirmation was given that safe routes to school were completed and open to the public.
The Forum raised questions on the update received, which were responded to by Grainger representatives and relevant officers as summarised below:
(a) A question was asked regarding the mud and condition of the southern allotments car park. Further clarification was provided that remedial works were proposed for the area.
(b) Concern was raised that the allotments were not yet at the stage of readiness suggested in the presentation.
(c) A query was raised regarding whether plans for shops within the village centre would be shared. It was noted that plans would be shared once they were formalised with the developer.
(d) Information was sought regarding meetings with the NHS concerning the health centre land. It was reported that a meeting had recently taken place involving the NHS and local representatives, initiated by Suella Braverman, MP to discuss obligations under the s106 agreement. A further meeting would be arranged with Grainger, the NHS and the developer delivering the GP surgery on behalf of the NHS in due course, with the intention of reporting back to the MP with an action plan within the next 4-6 weeks.
(e) The importance of communicating progress on the health centre to the district and parish council teams was emphasised so that residents could be kept informed with up-to-date communication.
(f) Comments were made regarding resident discontent with the rate of progress on site infrastructure.
(g) A question was asked regarding the management of reeds and vegetation within the sustainable urban drainage system (SUDs) and river areas. It was noted that the estate management company completed works and that ecologists provided positive feedback on wildlife levels in the River Wallington.
The Chair announced that it would be beneficial for ecologists to attend a future meeting of the forum to set out the management plan for these habitat systems and outline how the plan benefits these areas. Lea Hampton agreed to liaise with their ecologist to develop an approach.
RESOLVED:
That the report be received and the comments raised by the forum as set out above, be noted.