The Chairperson invited the members of the
public and visiting councillors to address the committee, and a
summary of their comments were as follows.
- Ian Tait addressed the committee. He
supported the proposals but questioned the provision of limited
parking, suggesting that city centre residents could live without
cars. He noted local opposition and emphasised the need for
community and ward councillor support, referencing past failed
schemes and questioned whether the council should manage the
project or seek alternative delivery routes.
- Lin Mellish addressed the committee.
She expressed a preference for council housing with social rents
rather than affordable housing, noting that the original intention
was for council homes. She stated that the lack of parking would
make the homes difficult to let due to unreliable public transport
and suggested that displaced vehicles would increase traffic,
concluding that whilst she wants homes, we need car parks and this
the car park should remain.
- Councillor Stephen Godfrey addressed
the committee. He highlighted three risks: the potential for cost
overruns on the design budget making the homes unaffordable, the
displacement of current car park users and the lack of alternative
spaces, and the risk of flooding on the site, noting a previous
failure to build a school there for that reason.
- Councillor Danny Lee addressed the
committee. He supported the use of the brownfield site for
affordable housing but questioned the financial assumptions, asking
for quantified evidence regarding displaced parking revenue. He
sought clarification on the uncommitted balance of Section 106
affordable housing funds, the actual available and eligible funds,
whether the expenditure would be released in stages, the value for
money of the design and build contract, and the risk of abortive
expenditure given Local Government Reorganisation and suggested to
accelerate the project or provide an additional gateway decision
point in order to minimise this risk.
Councillor Mark Reach, Cabinet Member for Good
Homes introduced the report, ref CAB3565, which set out proposals
regarding expenditure for professional fees to develop the scheme.
The introduction included the following points:
- The report sought a capital
expenditure of £480,000 for professional fees to develop the
scheme, which contributed to the target of 1,000 affordable homes
by 2032.
- The site was included in the Local
Plan for housing, and the current proposal aimed to deliver
approximately 44 homes, consisting of one and two-bedroom flats and
three-bedroom townhouses.
- The site was sustainable, though
groundwater and flood risks required assessment during the
pre-planning stage.
- The reduction of city centre parking
aligned with council strategy, and alternative parking provision
was available nearby and at park and ride sites.
- The tenure type was yet to be
finalised, but he believed that there was an opportunity to deliver
social housing and shared ownership units.
The Chairperson suggested that the Committee
consider the following points during discussion on the item:
- That the principle of residential
development on the site was established through the adopted Local
Plan.
- That the committee was not being
asked to approve construction, but rather to scrutinise the next
stage of work, including surveys, design, and planning application
preparation.
- That the committee should consider
the overall financial position, the impact of displaced parking on
council finances, and key delivery risks such as flooding,
archaeology, and ground conditions.
- That the final business case would
be considered in the context of local government reorganisation,
requiring the proposed work to provide sufficient information for a
future authority to make an informed decision.
The committee was recommended to comment on
the proposals within the attached report, ref CAB3565, which was to
be considered by cabinet at its meeting on 25 August 2026. The
committee proceeded to ask questions and debate the report. In
summary, the following matters were raised:
- A question was asked regarding the
£480,000 expenditure and how members could be satisfied it
was proportionate when no overall financial business case was
provided. A further question was asked whether the £480,000
would be released through defined project gateways and if members
would have an opportunity to review progress before the full amount
was committed.
- A question was asked regarding the
strategy and criteria used to bring sites forward, and the decision
process, as it was understood that this project was not on the list
at the July Cabinet Housing Committee. A further question was asked
if the decision criteria could be provided to members.
- Further clarification was sought
regarding viability costs, in relation to biodiversity net gain
(BNG), public realm maintenance, security risks, and ventilation in
the flats.
- A question was asked about how the
transfer of the site from the General Fund was assessed and whether
the potential increase in site value upon receiving planning
consent was included in the viability assessment.
- Further clarification was sought on
what controls, milestones, and reporting arrangements would be in
place to ensure value for money and limit abortive
expenditure.
- A question was asked regarding
flooding in the area, specifically water coming up through the
drains, and whether the budget for initial investigations was
sufficient to cover this issue.
- Clarification was sought regarding
the justification for increasing the proposed units from 30 in the
Local Plan to 44, and whether there would be further consultation
with residents. Further to this, it was asked if this point could
be taken back to the planning cabinet member.
- A question was asked regarding what
assurance could be provided that the £480,000 would not be
wasted if a successor council decided not to take the scheme
forward following local government reorganisation.
- It was asked whether it would be
acceptable to implement stage payments for the fees to manage
risks.
- Clarification was sought as to why
the land was not part of the Housing Revenue Account (HRA) at the
time it was originally identified for social housing.
- Further information was requested
regarding how the financial figures in the exempt appendix were
constructed and whether there was input from professionals.
- A question was asked regarding
parking and deliveries, and how delivery drivers and carers would
be accommodated given the lack of parking on site.
- Further information was asked about
housing need, and whether the model of provision matched the need
for central Winchester accommodation, including for one-bedroom
households.
The committee agreed to move into an exempt
session to consider the exempt appendix, during which further
questions were raised which included the following: public rights
of way and flooding considerations, professional survey fees, HRA
borrowing limits and assurance regarding budget estimates, the
inclusion of archaeology costs, and a request for a project plan
that would highlight key points and expenditure.
These points were responded to by Councillor
Mark Reach, Cabinet Member for Good Homes, Councillor Martin Tod,
Leader and Cabinet Member for Asset Management, Simon Hendey,
Strategic Director, Liz Keys, Director (Finance) and Caroline Egan,
Service Lead New Homes Delivery accordingly.
RESOLVED:
That the committee supported further
investigation of the site for affordable and social housing and
agreed to request that the following points be considered by
cabinet:
a)
That the final business case sets out the total estimated
development costs, the valuation and transfer arrangements relating
to the site, all funding sources, subsidy requirements, expected
rental income, borrowing requirements, the impact on HRA borrowing
capacity and long-term HRA business plan sustainability, and
sensitivity analysis for key risks.
b)
That the final business case provides an assessment of the impact
on parking provision, parking income, and any consequential effects
on the general fund.
c)
That the final business case includes an assessment of
site-specific risks identified through the investigation phase,
including archaeology, groundwater, flood risk, contamination, and
any associated mitigation measures, together with an explanation of
the impact of those risks on scheme viability, affordability, and
delivery timescales.
d)
That cabinet receives a decision point before the planning
application is submitted, setting out estimated development costs,
funding sources, and subsidy requirements, together with decision
gateways at which the continuing viability and affordability of the
scheme can be reviewed before further expenditure is committed.