Agenda item

Progress of Primary School 1 (verbal update)

Minutes:

 

Mr Yarrow, Property Services, Hampshire County Council (HCC) updated the forum regarding the progress of the works for Cornerstone Primary School. He advised that the contractor continued to make progress on site and it was expected for the school to be operational, as planned in September 2021.

 

Mr Clark, Headteacher, Cornerstone Primary school updated the forum on several matters including the plans for the physical relocation from the temporary site to the new one, which was scheduled to take place during July and August 2021.

 

Members asked several questions and made comments regarding; the dates of when equipment and resources would be moved into the school, the condition of the footpath leading to the school and the expected pupil numbers.

 

These points were responded to by HCC officers who reiterated the earlier comments regarding the footpath to the school and informed of ongoing discussions with the consortium to remedy this. Mr Yarrow agreed that a drawing showing the footpath links would be shared with members of the forum.

 

 

 

m - Progress of Primary School 1 (verbal update){sidenav}{content}